Here is the link to the fall sports streaming schedule.

https://appstatesports.com/news/2023/8/ ... edule.aspx

North End Zone Construction

User avatar
Rekdiver
Posts: 7525
Joined: Mon Aug 13, 2012 1:14 pm
School: Appalachian State
Has thanked: 1427 times
Been thanked: 3708 times

Re: North End Zone Construction

Unread post by Rekdiver » Thu Jul 18, 2019 1:03 pm

GregPercussion wrote:
Thu Jul 18, 2019 12:45 pm
Stonewall wrote:
Thu Jul 18, 2019 12:40 pm
I don't see the building being ready for the 2020 season opener.
I agree. But looks like they did something for the first time in weeks. They dug some holes today....
Must be Marines....they filling the holes back up.

Appstate88
Posts: 2647
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 526 times
Been thanked: 1427 times

Re: North End Zone Construction

Unread post by Appstate88 » Thu Jul 18, 2019 1:41 pm

Rekdiver wrote:
Thu Jul 18, 2019 1:03 pm
GregPercussion wrote:
Thu Jul 18, 2019 12:45 pm
Stonewall wrote:
Thu Jul 18, 2019 12:40 pm
I don't see the building being ready for the 2020 season opener.
I agree. But looks like they did something for the first time in weeks. They dug some holes today....
Must be Marines....they filling the holes back up.
My guess... Aggregate Piers. I'm not an engineer but did stay a Holiday Inn Express last night :lol:

https://www.haywardbaker.com/solutions/ ... gate-piers
GIVE 'EM HELL APPS!

User avatar
Gonzo
Posts: 4894
Joined: Mon Aug 27, 2012 2:11 pm
School: Appalachian State
Has thanked: 564 times
Been thanked: 1975 times

Re: North End Zone Construction

Unread post by Gonzo » Thu Jul 18, 2019 3:56 pm

BTK2000 wrote:
Thu Jul 18, 2019 9:37 am
So........ if there is not a tenant for the building how are they going to retire the giant loan they took out?

On the flip side western grad and I were taking about their p3 dorms. They have rental space for restaurants/ a tap room in their dorms as tenants to cover the retirement of the debt/ revenue. The only thing I could see that wouldn’t work at app is that it would break the monopoly food service has on campus and they wouldn’t be big fans of that. Oddly I think we are one of the few schools where our food service is a a school owned company and not contracted company.
Don’t we have Chic-fil-a and McAllister’s?

BTK2000
Posts: 420
Joined: Mon Oct 01, 2012 12:06 pm
School: Appalachian State
Has thanked: 33 times
Been thanked: 187 times

Re: North End Zone Construction

Unread post by BTK2000 » Thu Jul 18, 2019 4:28 pm

Gonzo wrote:
Thu Jul 18, 2019 3:56 pm
BTK2000 wrote:
Thu Jul 18, 2019 9:37 am
So........ if there is not a tenant for the building how are they going to retire the giant loan they took out?

On the flip side western grad and I were taking about their p3 dorms. They have rental space for restaurants/ a tap room in their dorms as tenants to cover the retirement of the debt/ revenue. The only thing I could see that wouldn’t work at app is that it would break the monopoly food service has on campus and they wouldn’t be big fans of that. Oddly I think we are one of the few schools where our food service is a a school owned company and not contracted company.
Don’t we have Chic-fil-a and McAllister’s?
I’m about 90% sure they are franchises owned and operated by Appalachian

BTK2000
Posts: 420
Joined: Mon Oct 01, 2012 12:06 pm
School: Appalachian State
Has thanked: 33 times
Been thanked: 187 times

Re: North End Zone Construction

Unread post by BTK2000 » Thu Jul 18, 2019 4:35 pm

/\PP ST/\TE GRAD 09 wrote:
Mon Jul 15, 2019 9:43 pm
BTK2000 wrote:
Mon Jul 15, 2019 7:54 pm
NewApp wrote:
Mon Jul 15, 2019 5:21 pm
appgrouch wrote:
Mon Jul 15, 2019 10:16 am
/\PP ST/\TE GRAD 09 wrote:
Sat Jul 13, 2019 10:47 pm


Not a single outdoor track meet in Boone this past season. I would expect a similar schedule this coming year.
As of right now, the team will not have a full practice or competition until 2021 at the earliest.

The original plan was to work on the track first, then tennis and then softball. The track because of NEZP, then Tennis for addition tower parking for Athletics and $$$$$$$$$$$$ Yosef, and then the softball to expand Sofield. Then sometime around April, someone came up with funds/donation to get started on Sofield, so Softball, who currently has a field, jumped to the top of the list. The track will happen:
Katers said the tennis and track and field facilities will be built as part of phase two “when funding allows.”
The track will happen when?
I think the track would look great with the new endzone facility in the background. Putting the track in the stadium would really highlight that program at Appalachian
Glad to see I'm not the only one who heard this ground breaking news. This part of the project is towards the end, right before the addition of soccer and field hockey lines. Letterhead style endzones, if the budget permits. Also, the band will be on the hill in efforts to project the noise to the new facility.
I also think we should update the sound system in the stadium so that we can play more music in the stadium. It would really help to enhance the fan game day experience. Other schools promote their well know alumni and I think it would be cool to have Eric church do something with the pregame video to really pump up the crowd

APP72
Posts: 564
Joined: Thu Dec 07, 2000 11:27 pm
School: Appalachian State
Location: Cherryville, N.C.
Has thanked: 2304 times
Been thanked: 43 times

Re: North End Zone Construction

Unread post by APP72 » Thu Jul 18, 2019 8:13 pm

LUKE COMBS!!!!
A CHAMPION IS SOMEONE WHO GETS UP WHEN HE CAN’T!
JACK DEMPSEY

APP72
Posts: 564
Joined: Thu Dec 07, 2000 11:27 pm
School: Appalachian State
Location: Cherryville, N.C.
Has thanked: 2304 times
Been thanked: 43 times

Re: North End Zone Construction

Unread post by APP72 » Thu Jul 18, 2019 8:13 pm

LUKE COMBS!!!!
A CHAMPION IS SOMEONE WHO GETS UP WHEN HE CAN’T!
JACK DEMPSEY

AppOrange
Posts: 1339
Joined: Wed Sep 09, 2015 7:28 pm
School: Appalachian State
Location: Raleigh
Has thanked: 997 times
Been thanked: 645 times
Contact:

Re: North End Zone Construction

Unread post by AppOrange » Thu Jul 18, 2019 8:59 pm

anyone got that link to the construction cams?
1996

Appstate88
Posts: 2647
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 526 times
Been thanked: 1427 times

Re: North End Zone Construction

Unread post by Appstate88 » Thu Jul 18, 2019 9:12 pm

AppOrange wrote:
Thu Jul 18, 2019 8:59 pm
anyone got that link to the construction cams?
Here you go AppOrange.
http://www.resortcams.com/webcams/app-s ... dzone-cam/
GIVE 'EM HELL APPS!

User avatar
Rekdiver
Posts: 7525
Joined: Mon Aug 13, 2012 1:14 pm
School: Appalachian State
Has thanked: 1427 times
Been thanked: 3708 times

Re: North End Zone Construction

Unread post by Rekdiver » Thu Jul 18, 2019 9:53 pm

BTK2000 wrote:
Thu Jul 18, 2019 4:35 pm
/\PP ST/\TE GRAD 09 wrote:
Mon Jul 15, 2019 9:43 pm
BTK2000 wrote:
Mon Jul 15, 2019 7:54 pm
NewApp wrote:
Mon Jul 15, 2019 5:21 pm
appgrouch wrote:
Mon Jul 15, 2019 10:16 am


As of right now, the team will not have a full practice or competition until 2021 at the earliest.

The original plan was to work on the track first, then tennis and then softball. The track because of NEZP, then Tennis for addition tower parking for Athletics and $$$$$$$$$$$$ Yosef, and then the softball to expand Sofield. Then sometime around April, someone came up with funds/donation to get started on Sofield, so Softball, who currently has a field, jumped to the top of the list. The track will happen:
The track will happen when?
I think the track would look great with the new endzone facility in the background. Putting the track in the stadium would really highlight that program at Appalachian
Glad to see I'm not the only one who heard this ground breaking news. This part of the project is towards the end, right before the addition of soccer and field hockey lines. Letterhead style endzones, if the budget permits. Also, the band will be on the hill in efforts to project the noise to the new facility.
I also think we should update the sound system in the stadium so that we can play more music in the stadium. It would really help to enhance the fan game day experience. Other schools promote their well know alumni and I think it would be cool to have Eric church do something with the pregame video to really pump up the crowd
You are kidding right?

User avatar
Rekdiver
Posts: 7525
Joined: Mon Aug 13, 2012 1:14 pm
School: Appalachian State
Has thanked: 1427 times
Been thanked: 3708 times

Re: North End Zone Construction

Unread post by Rekdiver » Thu Jul 18, 2019 9:56 pm

Appstate88 wrote:
Thu Jul 18, 2019 1:41 pm
Rekdiver wrote:
Thu Jul 18, 2019 1:03 pm
GregPercussion wrote:
Thu Jul 18, 2019 12:45 pm
Stonewall wrote:
Thu Jul 18, 2019 12:40 pm
I don't see the building being ready for the 2020 season opener.
I agree. But looks like they did something for the first time in weeks. They dug some holes today....
Must be Marines....they filling the holes back up.
My guess... Aggregate Piers. I'm not an engineer but did stay a Holiday Inn Express last night :lol:

https://www.haywardbaker.com/solutions/ ... gate-piers
Well you are dead on.

Appstate88
Posts: 2647
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 526 times
Been thanked: 1427 times

Re: North End Zone Construction

Unread post by Appstate88 » Fri Jul 19, 2019 12:26 pm

1st Concrete Truck has arrived on NEZ project site.

http://www.resortcams.com/webcams/app-s ... dzone-cam/
GIVE 'EM HELL APPS!

BooneKarate
Posts: 129
Joined: Wed Jul 03, 2019 7:50 am
School: Appalachian State
Has thanked: 62 times
Been thanked: 21 times

Re: North End Zone Construction

Unread post by BooneKarate » Fri Jul 19, 2019 1:04 pm

Rekdiver wrote:
Thu Jul 18, 2019 9:53 pm
BTK2000 wrote:
Thu Jul 18, 2019 4:35 pm
/\PP ST/\TE GRAD 09 wrote:
Mon Jul 15, 2019 9:43 pm
BTK2000 wrote:
Mon Jul 15, 2019 7:54 pm
NewApp wrote:
Mon Jul 15, 2019 5:21 pm


The track will happen when?
I think the track would look great with the new endzone facility in the background. Putting the track in the stadium would really highlight that program at Appalachian
Glad to see I'm not the only one who heard this ground breaking news. This part of the project is towards the end, right before the addition of soccer and field hockey lines. Letterhead style endzones, if the budget permits. Also, the band will be on the hill in efforts to project the noise to the new facility.
I also think we should update the sound system in the stadium so that we can play more music in the stadium. It would really help to enhance the fan game day experience. Other schools promote their well know alumni and I think it would be cool to have Eric church do something with the pregame video to really pump up the crowd
You are kidding right?
To be fair, there are only speakers on one end of the stadium. I think they're in the jumbo-tron. There's no happy medium between blasting the hill and having good sound on the other end of the stadium. They should put smaller speakers above certain sections to balance it out, but there's no telling what cost that comes at and it's definitely not an expense that you can get a sponsor to cover. Pure expense. Probably not quite worth it at this point.

User avatar
Rekdiver
Posts: 7525
Joined: Mon Aug 13, 2012 1:14 pm
School: Appalachian State
Has thanked: 1427 times
Been thanked: 3708 times

Re: North End Zone Construction

Unread post by Rekdiver » Fri Jul 19, 2019 2:52 pm

Appstate88 wrote:
Fri Jul 19, 2019 12:26 pm
1st Concrete Truck has arrived on NEZ project site.

http://www.resortcams.com/webcams/app-s ... dzone-cam/
I think the've hit water.....

NewApp
Posts: 7491
Joined: Tue Mar 26, 2013 8:59 am
School: Appalachian State
Has thanked: 958 times
Been thanked: 900 times
Contact:

Re: North End Zone Construction

Unread post by NewApp » Tue Jul 23, 2019 8:37 am

Rekdiver wrote:
Fri Jul 19, 2019 2:52 pm
Appstate88 wrote:
Fri Jul 19, 2019 12:26 pm
1st Concrete Truck has arrived on NEZ project site.

http://www.resortcams.com/webcams/app-s ... dzone-cam/
I think the've hit water.....
Too bad it's not oil...then we could pay for everything, and more, up front. Just kidding, of course.
NewApp formerly known as JCline
If you can't take it, don't dish it out.
Google SUX

Appstate88
Posts: 2647
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 526 times
Been thanked: 1427 times

Re: North End Zone Construction

Unread post by Appstate88 » Wed Jul 31, 2019 7:02 am

GIVE 'EM HELL APPS!

sixtoes9134
Posts: 1245
Joined: Fri Aug 10, 2012 5:42 am
Has thanked: 59 times
Been thanked: 278 times

Re: North End Zone Construction

Unread post by sixtoes9134 » Wed Jul 31, 2019 7:06 am

Appstate88 wrote:
Wed Jul 31, 2019 7:02 am
All Quiet on the NEZ Front.

http://www.resortcams.com/webcams/app-s ... zone-cam//
They just finished 2 weeks of underground supports (aggregate piers). Seems like they should be ready to roll now. It will be disappointing if things don't start moving quickly now for sure.

ASU84
Posts: 492
Joined: Wed Dec 26, 2012 9:26 pm
School: Appalachian State
Location: Welcome, NC
Has thanked: 1242 times
Been thanked: 168 times
Contact:

Re: North End Zone Construction

Unread post by ASU84 » Wed Jul 31, 2019 7:25 am

sixtoes9134 wrote:
Wed Jul 31, 2019 7:06 am
Appstate88 wrote:
Wed Jul 31, 2019 7:02 am
All Quiet on the NEZ Front.

http://www.resortcams.com/webcams/app-s ... zone-cam//
They just finished 2 weeks of underground supports (aggregate piers). Seems like they should be ready to roll now. It will be disappointing if things don't start moving quickly now for sure.
Must be having a VIP meeting in the command trailer this morning. At least 6 vehicles and no one in sight.

User avatar
beav910
Posts: 511
Joined: Wed Dec 17, 2014 9:13 pm
School: Appalachian State
Has thanked: 76 times
Been thanked: 162 times

Re: North End Zone Construction

Unread post by beav910 » Wed Jul 31, 2019 9:47 am

Any word on if the track is being covered by the start of the season? I know it’s probably low on the list of priorities but I was just curious.
Appalachian State Alumnus :: Graphic Designer

User avatar
GregPercussion
Posts: 623
Joined: Fri Mar 02, 2018 2:01 pm
School: Appalachian State
Has thanked: 243 times
Been thanked: 194 times

Re: North End Zone Construction

Unread post by GregPercussion » Wed Jul 31, 2019 10:00 am

beav910 wrote:
Wed Jul 31, 2019 9:47 am
Any word on if the track is being covered by the start of the season? I know it’s probably low on the list of priorities but I was just curious.
I don't think there's an official word. But no way. Not at least until the foundation is established for the NEZ.

Post Reply Previous topicNext topic