Re: Appstate Endzone Camera

Unread post by HkyMtneer » Thu May 02, 2019 6:29 pm

Saint3333 wrote:
Thu May 02, 2019 2:47 pm
I have to wonder how fund raising is going with these delays.
I've also been curious about this, especially with all the recent changes in the athletics development office that appears to have occurred...though we haven't heard much about those.



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Fri May 03, 2019 3:29 pm

Saint3333 wrote:
Thu May 02, 2019 2:47 pm
I have to wonder how fund raising is going with these delays.
Chicken or Egg.


That's what I do. I gripe and I know things.

User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Mon May 13, 2019 2:59 pm

Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020


That's what I do. I gripe and I know things.

NewApp
Posts: 4106
Joined: Tue Mar 26, 2013 8:59 am
School: Appalachian State
Has thanked: 347 times
Been thanked: 320 times

Re: Appstate Endzone Camera

Unread post by NewApp » Mon May 13, 2019 6:30 pm

appgrouch wrote:
Mon May 13, 2019 2:59 pm
Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020
Aren't hydrotherapy and weight training already available in the present complex?



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Tue May 14, 2019 7:28 am

NewApp wrote:
Mon May 13, 2019 6:30 pm
appgrouch wrote:
Mon May 13, 2019 2:59 pm
Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020
Aren't hydrotherapy and weight training already available in the present complex?
Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.


That's what I do. I gripe and I know things.

Appstate88
Posts: 1008
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 168 times
Been thanked: 454 times

Re: Appstate Endzone Camera

Unread post by Appstate88 » Tue May 14, 2019 11:10 am

appgrouch wrote:
Tue May 14, 2019 7:28 am
NewApp wrote:
Mon May 13, 2019 6:30 pm
appgrouch wrote:
Mon May 13, 2019 2:59 pm
Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020
Aren't hydrotherapy and weight training already available in the present complex?
Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.

What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Tue May 14, 2019 11:52 am

Appstate88 wrote:
Tue May 14, 2019 11:10 am
appgrouch wrote:
Tue May 14, 2019 7:28 am
NewApp wrote:
Mon May 13, 2019 6:30 pm
appgrouch wrote:
Mon May 13, 2019 2:59 pm
Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020
Aren't hydrotherapy and weight training already available in the present complex?
Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.

What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.
Demo started late and no footings have been poured as of yet.

https://physicalplant.appstate.edu/news ... ummer-2019


That's what I do. I gripe and I know things.

Appstate88
Posts: 1008
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 168 times
Been thanked: 454 times

Re: Appstate Endzone Camera

Unread post by Appstate88 » Tue May 14, 2019 12:09 pm

appgrouch wrote:
Tue May 14, 2019 11:52 am
Appstate88 wrote:
Tue May 14, 2019 11:10 am
appgrouch wrote:
Tue May 14, 2019 7:28 am
NewApp wrote:
Mon May 13, 2019 6:30 pm
appgrouch wrote:
Mon May 13, 2019 2:59 pm
Kidd Brewer Stadium – North End Zone
Construction of a new multi-story building to include a kitchen for catering events on campus, beautiful meeting and banquet space, coaches' offices, locker rooms, weight training, hydrotherapy, a team store, ticketing, nutrition science research areas, and premium seating for 1,000 football fans.

Why? Owens, like many of us, was starting to decline at 45 years old. The new facility will provide much needed year-round meeting space and puts a great face on the entrance to the stadium.

Current-December 2020
Aren't hydrotherapy and weight training already available in the present complex?
Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.

What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.
Demo started late and no footings have been poured as of yet.

https://physicalplant.appstate.edu/news ... ummer-2019
If the NEZ project can't be completed in time for the 2020 Football Season, this information should be updated.
https://mountaineerimpact.com/end-zone- ... index.html



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Tue May 14, 2019 12:34 pm

Appstate88 wrote:
Tue May 14, 2019 12:09 pm
appgrouch wrote:
Tue May 14, 2019 11:52 am
Appstate88 wrote:
Tue May 14, 2019 11:10 am
appgrouch wrote:
Tue May 14, 2019 7:28 am
NewApp wrote:
Mon May 13, 2019 6:30 pm


Aren't hydrotherapy and weight training already available in the present complex?
Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.

What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.
Demo started late and no footings have been poured as of yet.

https://physicalplant.appstate.edu/news ... ummer-2019
If the NEZ project can't be completed in time for the 2020 Football Season, this information should be updated.
https://mountaineerimpact.com/end-zone- ... index.html
Doesn't say "2020 Season", just says 2020 as expected date.


That's what I do. I gripe and I know things.

User avatar
goapps93
Posts: 2761
Joined: Sat Sep 08, 2007 1:48 pm
Has thanked: 58 times
Been thanked: 155 times

Re: Appstate Endzone Camera

Unread post by goapps93 » Tue May 14, 2019 1:13 pm

Reading that maintenance report shows that there is a sense of humor within the Physical Plant.


WE ARE YOSEF!

Appstate88
Posts: 1008
Joined: Mon Dec 24, 2012 9:38 am
School: Appalachian State
Has thanked: 168 times
Been thanked: 454 times

Re: Appstate Endzone Camera

Unread post by Appstate88 » Tue May 14, 2019 1:18 pm

appgrouch wrote:
Tue May 14, 2019 12:34 pm
Appstate88 wrote:
Tue May 14, 2019 12:09 pm
appgrouch wrote:
Tue May 14, 2019 11:52 am
Appstate88 wrote:
Tue May 14, 2019 11:10 am
appgrouch wrote:
Tue May 14, 2019 7:28 am


Prior to Owens coming down, the facilities in the tower was primarily FB and BBall(?) only. A majority of the other sports were still using the WT & AT in Owens.

The main reason I posted that was that the date is currently Dec of 2020 for completion.

What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.
Demo started late and no footings have been poured as of yet.

https://physicalplant.appstate.edu/news ... ummer-2019
If the NEZ project can't be completed in time for the 2020 Football Season, this information should be updated.
https://mountaineerimpact.com/end-zone- ... index.html
Doesn't say "2020 Season", just says 2020 as expected date.
Gotcha, Understand... I was talking about this part of the website that talks about securing your seats for the 2020 season....

Club Seats
Seat Agreements
Seat Agreements available for 3, 5 or 7 years
Initial Seat License
Initial seat license gift of $1,000 per seat
Annual Seat Cost
Annual seat cost of $1,000 per seat due by April 30 each year of seat ownership
(due by April 30, 2020 prior to first season)

Seat Deposit Payment Plan Option
25% of total seat deposit must be paid by July 1, 2019, remainder by December 31, 2019
Secure Club Seats Today
Loge Boxes
Seat Agreements
Seat Agreements available for 3, 5 or 7 years
Initial Seat License
Initial seat license gift of $1,000 per seat
Annual Seat Cost
Annual seat cost of $2,500 per seat due by April 30 each year of seat ownership
(due by April 30, 2020 prior to first season)
Seat Deposit Payment Plan Option
25% of total seat deposit must be paid by July 1, 2019, remainder by December 31, 2019



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Tue May 14, 2019 1:50 pm

Appstate88 wrote:
Tue May 14, 2019 1:18 pm
appgrouch wrote:
Tue May 14, 2019 12:34 pm
Appstate88 wrote:
Tue May 14, 2019 12:09 pm
appgrouch wrote:
Tue May 14, 2019 11:52 am
Appstate88 wrote:
Tue May 14, 2019 11:10 am



What is your source for Dec 2020? I was still tracking Aug 2020 in time for home opener.
Demo started late and no footings have been poured as of yet.

https://physicalplant.appstate.edu/news ... ummer-2019
If the NEZ project can't be completed in time for the 2020 Football Season, this information should be updated.
https://mountaineerimpact.com/end-zone- ... index.html
Doesn't say "2020 Season", just says 2020 as expected date.
Gotcha, Understand... I was talking about this part of the website that talks about securing your seats for the 2020 season....

Club Seats
Seat Agreements
Seat Agreements available for 3, 5 or 7 years
Initial Seat License
Initial seat license gift of $1,000 per seat
Annual Seat Cost
Annual seat cost of $1,000 per seat due by April 30 each year of seat ownership
(due by April 30, 2020 prior to first season)

Seat Deposit Payment Plan Option
25% of total seat deposit must be paid by July 1, 2019, remainder by December 31, 2019
Secure Club Seats Today
Loge Boxes
Seat Agreements
Seat Agreements available for 3, 5 or 7 years
Initial Seat License
Initial seat license gift of $1,000 per seat
Annual Seat Cost
Annual seat cost of $2,500 per seat due by April 30 each year of seat ownership
(due by April 30, 2020 prior to first season)
Seat Deposit Payment Plan Option
25% of total seat deposit must be paid by July 1, 2019, remainder by December 31, 2019
To the Athletic department it is "Oh god Oh god, we have got to get this done before the season"
To the Physical Plant/Desn&Const it is "After all that will go wrong, how long will this take."


That's what I do. I gripe and I know things.

User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Tue May 14, 2019 1:52 pm

goapps93 wrote:
Tue May 14, 2019 1:13 pm
Reading that maintenance report shows that there is a sense of humor within the Physical Plant.
You call is a sense of humor, the Psy Dept calls it a case study.
https://physicalplant.appstate.edu/news ... s-solution


That's what I do. I gripe and I know things.

User avatar
goapps93
Posts: 2761
Joined: Sat Sep 08, 2007 1:48 pm
Has thanked: 58 times
Been thanked: 155 times

Re: Appstate Endzone Camera

Unread post by goapps93 » Tue May 14, 2019 8:09 pm

appgrouch wrote:
Tue May 14, 2019 1:52 pm
goapps93 wrote:
Tue May 14, 2019 1:13 pm
Reading that maintenance report shows that there is a sense of humor within the Physical Plant.
You call is a sense of humor, the Psy Dept calls it a case study.
https://physicalplant.appstate.edu/news ... s-solution
Heh, tomato/potato. :D


WE ARE YOSEF!

User avatar
APPdiesel
Posts: 1063
Joined: Thu Jul 16, 2015 5:53 pm
School: Appalachian State
Has thanked: 151 times
Been thanked: 424 times

Re: Appstate Endzone Camera

Unread post by APPdiesel » Fri May 17, 2019 3:27 pm

I see they've started bringing in concrete piping. I saw a concrete truck out there yesterday but they didn't pour anything. Anybody know when they plan to start digging foundation?


"Sports talk's most decent producer" on ESPN Upstate

http://www.twitter.com/dieselonradio

Apple@chin1
Posts: 73
Joined: Wed Oct 03, 2018 3:19 pm
School: Appalachian State
Location: Hobe Sound, Fl.
Has thanked: 94 times
Been thanked: 46 times

Re: Appstate Endzone Camera

Unread post by Apple@chin1 » Thu May 30, 2019 7:57 am

It looks like they’re resuming construction. It seemed like it came to a halt for a few weeks. Nice to see progress.



User avatar
appgrouch
Posts: 1021
Joined: Tue Feb 16, 2010 3:36 pm
School: Appalachian State
Location: In my seat, waiting for people to shut up and play.
Has thanked: 4 times
Been thanked: 80 times

Re: Appstate Endzone Camera

Unread post by appgrouch » Thu May 30, 2019 8:32 am

Apple@chin1 wrote:
Thu May 30, 2019 7:57 am
It looks like they’re resuming construction. It seemed like it came to a halt for a few weeks. Nice to see progress.
Right now it is mostly storm water and steam line which are part of the P3 project and the NEZ project.


That's what I do. I gripe and I know things.

User avatar
StorminASU
Posts: 218
Joined: Fri Aug 10, 2012 1:30 pm
School: Appalachian State
Location: Boone, NC
Has thanked: 176 times
Been thanked: 56 times

Re: Appstate Endzone Camera

Unread post by StorminASU » Thu May 30, 2019 9:22 am

goapps93 wrote:
Tue May 14, 2019 1:13 pm
Reading that maintenance report shows that there is a sense of humor within the Physical Plant.
That was the most entertaining maintenance report I've ever read through...probably the only one I've ever read through, haha.



User avatar
asu66
Posts: 25609
Joined: Tue Jun 27, 2000 1:21 pm
School: Appalachian State
Has thanked: 977 times
Been thanked: 1225 times

Re: Appstate Endzone Camera

Unread post by asu66 » Thu May 30, 2019 1:43 pm

If all of the indoor space isn't enclosed by mid-Nov., the fall-2020 open house festivities will be seriously at risk. The gen. contractors and subs may be working 24x7 shifts this time next year.


If it happens to the Apps, it happens to me!

WASU 93
Posts: 174
Joined: Sat Sep 05, 2015 10:51 pm
School: Appalachian State
Has thanked: 88 times
Been thanked: 87 times

Re: Appstate Endzone Camera

Unread post by WASU 93 » Thu May 30, 2019 10:48 pm

Perhaps the seating is completed for the start of the 2020 Season and the indoor areas are not completed until later that Winter. Purely speculation, but they could put an emphasis on the revenue producing part of the project and bring the rest of the facility online later.



Post Reply Previous topicNext topic

Return to “Appalachian General Discussion”

  • Who is online
  • In total there are 37 users online :: 2 registered, 0 hidden and 35 guests

    Most users ever online was 1551 on Sun Sep 02, 2018 4:31 pm

    Users browsing this forum: CVAPP, msinclair and 35 guests